A multimillion-dollar plan to improve the Monroe County (Indiana) Airport lighting system will continue to be delayed through the spring according to airport officials, as supply chain issues strike again.

The airport received a $2.3 million federal grant in 2020 to replace the old incandescent lighting system with brighter, more efficient LEDs, Indiana Public Media reports.

Shipping and manufacturing delays for materials have drawn the project out almost three years. Some of the parts required for the project have been delayed more than 16 months, officials say.

Read the story.

Source: Indiana Public Media

About the Author

Frank Raczon

Raczon’s writing career spans nearly 25 years, including magazine publishing and public relations work with some of the industry’s major equipment manufacturers. He has won numerous awards in his career, including nods from the Construction Writers Association, the Association of Equipment Manufacturers, and BtoB magazine. He is responsible for the magazine's Buying Files.

Sign up for Construction Equipment eNewsletters
Get the latest news and updates