Rehabilitating Water Main

The city of Monroe, MI, recently awarded an important water main rehabilitation project to Insituform Technologies USA, Inc. of St. Louis, MO. Insituform is rehabilitating 2.5 miles of water main in Monroe using a special process that lines the existing pipe. "We decided to go with the Insituform Blue® system for a couple of reasons — the first is that the water main pipe is still go...

January 19, 2009

The city of Monroe, MI, recently awarded an important water main rehabilitation project to Insituform Technologies USA, Inc. of St. Louis, MO. Insituform is rehabilitating 2.5 miles of water main in Monroe using a special process that lines the existing pipe.

"We decided to go with the Insituform Blue® system for a couple of reasons — the first is that the water main pipe is still good, we really just needed to clean it out and shore it up," said Patrick Lewis, Monroe's director of Engineering. "Second, that application (lining water main pipe) really worked well for this situation. There aren't a lot of leads along the line, and it really provided minimal disruption to the area's traffic, so that alone provided a cost savings."

Insituform is lining the water main using its Thermopipe® system. The Thermopipe liner is a thin, reinforced polyethylene liner ideally suited for rehabilitation of distribution water mains and other pressurized piping systems up to 12 inches in diameter. Supplied as a factory-folded "C" shape liner, the Thermopipe liner is winched into the host pipe from a reel and reverted with air and steam. Once inflated and heated, the liner forms a close fit within the host pipe, creating a jointless, leak-free lining system able to independently carry the full system internal design pressure.

In total, more than 14,000 linear feet of water main will be lined by Insituform over a 2.5-mile area. Along the pipeline, the watermain will be accessed between 120 to 140 times, wherever there is a hydrant, tee in the line, or valve.

Even though the water main isn't particularly deep in the ground (between 5 and 8 feet deep), making multiple excavations in a busy area of Monroe creates its own unique challenges. Insituform requires the ability to access the host pipes for cleaning, lining and post-rehabilitation inspection. Multiple small pits will need to be dug and then left open for access — as many as 21 holes at one time. Although pits will be cut directly in the middle of busy roads, resulting in some lane closures and other traffic redirects, the installation of the Thermopipe system will be less disruptive than traditional dig and replace methods.

Each pit will be dug out with a rubber-track mini-excavator, which is smaller than an excavator typically used in this situation. The trench shoring for the pits will also be installed with smaller equipment. The perfect shoring solution for subcontractor Rachel Contracting, LLC, of Minnesota, is the lightweight, modular Build-A-Box™ Aluminum Trench Shielding System manufactured by Efficiency Production, Inc. of Mason, MI. Rachel Contracting is responsible for all of the excavations, shoring and plumbing on the project.

"I like the (aluminum modular) boxes," Mark Hairston, Insituform's project supervisor, said. "We were using end shores and boards before, but the guys really like using the four-sided boxes. It's so easy — just cut a hole to fit the box, and set it with a backhoe."

Where the water main is accessed, the pits will be kept relatively tight. Rachel Contracting is using a series of 5-foot by 10-foot, four-sided aluminum trench shields put together using 2-foot-high aluminum Build-A-Box panels and 8-foot tall full-length corner posts. The panels are secured in the corner posts with a series of pins and keepers.

Efficiency Production's Build-A-Box is one of the most flexible trench shielding systems available and is able to be assembled into two-, three-, and four-sided configurations, plus three-way tee configurations and other spot-utility shoring. Custom accessorized Barrier Posts integrate seamlessly into the corner posts of each Build-A-Box unit, making it the perfect fall protection system for the shored pits dug in the middle of the road.

"The Build-A-Box is very flexible," Scott Weaver, Rachel Contracting's foreman on the project, said. "There have been places where we've needed to add depth, so we've simply added another panel to the top of the box, and in some places we've needed to leave out a panel near the bottom to get around a cross utility."

After installing and reverting the Thermopipe liner in the host pipe, Insituform renews service connections to the water main using its exclusive iTAP® system, a robotic method of reinstating service connections from inside a lined water main. A remote operator uses an innovative technology to locate the service connections and robotically cuts through the liner at each service opening. A special device is used to tap each corporation valve. As a final step, a sealing nut and gasket are installed in each threaded corporation valve, creating a water-tight seal.

The $2.5-million water main restoration project began in October 2008, and it is expected to be completed in spring 2009.


Author Information
James McRay is director of Marketing and Media at Efficiency Production, Inc.

 

Project: Water main rehabilitation in Monroe, MI

Contractor: Rachel Contracting, LLC, of Minnesota

Cost: $2.5 million