Construction on the new Vikings Stadium is nearly halfway complete

March 30, 2015

Construction on the new Vikings Stadium is nearly halfway complete. Mortenson Construction, the project contractor, said it will reach the halfway mark by the end of April.

The stadium has been under construction since Dec. 3, 2013 and is expected to be finished in July 2016.

Construction is projected to cost $1.061 billion. The state of Minnesota is paying $348 million, the city of Minneapolis is paying an additional $150 million and the Vikings team is contributing $550 million. 

Source: MPR News